If the project identifier is a number (i.e. 1663), no tasks are be displayed in the summary on the planning session, when is enabled "Display summary below" and "Display"/"Projects planning".
Only task related to project identifier starting with a character, are working well.
Would be possible to fix it ?
Thx
F.
Missing task on 'Display summary' if project ID is number
-
- Site Admin
- Posts: 395
- Joined: 31 Aug 2017, 15:58
Re: Missing task on 'Display summary' if project ID is number
Sorry for the late answer.
The problem is fixed and will be available in next version coming soon
The problem is fixed and will be available in next version coming soon