If the project identifier is a number (i.e. 1663), no tasks are be displayed in the summary on the planning session, when is enabled "Display summary below" and "Display"/"Projects planning".
Only task related to project identifier starting with a character, are working well.
Would be possible to fix it ?
Thx
F.
Missing task on 'Display summary' if project ID is number
-
- Site Admin
- Posts: 396
- Joined: 31 Aug 2017, 15:58
Re: Missing task on 'Display summary' if project ID is number
Sorry for the late answer.
The problem is fixed and will be available in next version coming soon