Post by Rqk »

wouldnt it make more sense to have the task name in the summary under people planning instead of just the name again? see picture
Attachments
planner.jpg
planner.jpg (64.91 KiB) Viewed 24525 times
soplanning
Site Admin
Posts: 399
Joined: 31 Aug 2017, 15:58

Re: People planning summary

Post by soplanning »

If you fill a task title, it should appear just after the people name !
Rqk
Posts: 6
Joined: 29 May 2020, 08:06

Re: People planning summary

Post by Rqk »

that makes sense..

but then projekt name instead of people name again?
soplanning
Site Admin
Posts: 399
Joined: 31 Aug 2017, 15:58

Re: People planning summary

Post by soplanning »

Yes it could be that way, we'll think about it
In fact, if you switch to the project view, it's more relevant.
Rqk
Posts: 6
Joined: 29 May 2020, 08:06

Re: People planning summary

Post by Rqk »

i also think that you could do the same in project view, just with person name.

maybe i doesnt make sense to others, it would just help me more, than having the same information twice. :)